Purple Line Won’t Open Until at Least Mid-2027 After Another Delay

Courtesy of Purple Line

The Purple Line won’t go into service until at least mid-2027.

The long-awaited light rail line faces another construction-related delay, this time due to unexpected complications moving utility lines.

The additional seven months come on top of other delays that put the project four and a half years behind schedule. The 16-mile transit line was originally supposed to open last year.

The project’s backers had hoped that a new contractor, the end of the pandemic and the resolution of lawsuits from Chevy Chase residents would mean a fresh start.

State officials told the Washington Post, which first obtained the report that included the new delay, that they are looking for other ways to speed up construction.

“Building a complex transportation project through a 16-mile corridor of vibrant and active communities is never going to be an easy task,” spokesman David Abrams said.

Support the Wire and Community Journalism
Make a one-time donation or become a regular supporter here.

This entry was posted in College Park and tagged , , , . Bookmark the permalink.

Subscribe to Blog via Email

Enter your email address to subscribe to this
blog and receive notifications of new posts by email.

Discover more from

Subscribe now to keep reading and get access to the full archive.

Continue reading